The church was prepared for Confirmation services. It looked very nice for the service. Work will begin these next two weeks on stripping the paint on the walls and installing the stone floor, that was delivered on Monday.
Tuesday, March 30, 2010
Saturday, March 27, 2010
Thursday, March 25, 2010
Concrete has been poured!!
Monday, March 22, 2010
Church Organ Pipes
Roof work and ready to pour concrete inside
The shingles on the roof have been torn down and replaced. You can see they have been working on the plaster inside the church. Also, they finished tying the steel on Friday to prepare to pour the concrete on the inside of the church. Monday morning, the concrete was poured.
Monday--Gables, Pews and Steeple Photos
Workers can be seen tacking up the siding on the back gable of the church to better secure it. A lot of progress is being made on the pews. Broken pieces have been replaced on some and the painting process has begun on many of the pews. Workers can be seen checking out the conditions on the tower and steeple.
Wednesday, March 17, 2010
Wed--Roof and Plaster Work
Plaster and inside work continues
Friday, March 12, 2010
Friday--Sidewalk and plaster work continues...
The sidewalk from the church office to the school has been poured. Traeco has been working on reconnecting the air conditioning units to the church.
Friday--Hole in the center of the chuch floor
Thursday, March 11, 2010
Thursday--Inside floors completely removed!
Tuesday, March 9, 2010
Tuesday--Floor on inside of church is gone!
By the end of the day Friday, all the concrete from the sides and middle that was busted up, was all cleaned up and hauled out of the church. On Monday, the demolition of the entire floor in the sanctuary was completed. They are now working on the removal of all the rock and busted up concrete.
You can see by the picture that the pillars are sitting on stone which appears to have been carved into the shape you see. Those stones seem to be a different type of rock from the stones they found under the concrete and from the stones that make up the walls of the church.
Today they are working on busting up the concrete in the back rooms and entrance of the church, as well as continuing to haul out rocks from inside the church. Crews also continue to work on the plaster on the south side of the church.
You can see by the picture that the pillars are sitting on stone which appears to have been carved into the shape you see. Those stones seem to be a different type of rock from the stones they found under the concrete and from the stones that make up the walls of the church.
Today they are working on busting up the concrete in the back rooms and entrance of the church, as well as continuing to haul out rocks from inside the church. Crews also continue to work on the plaster on the south side of the church.
Progress on the Organ--Pedal Pipes!
Here are some more pictures sent by Friedemann, the gentleman who is restoring the church organ, in Florida. These pictures are of the pedal chest on which the pipes sit that are played by the feet. He found that most of the pedal pipes have loose joints and cracks and need re-gluing. He also noted that the small pedal pipes now have new long feet to let the bass speak out. Fascinating!
Subscribe to:
Posts (Atom)